The 2000 m road paving project consists of the following activities:(in order Important notes: The contract was
Question:
The 2000 m road paving project consists of the following activities:(in order
Important notes: The contract was made as follows:
The first activity A is carried out by one working group from the start of the road.
The second activity B is carried out by two groups, the first from the beginning of the road and starts twenty days after the start of activity A and the second from the middle of the road and starts fifteen days after the end of activity A for the first half.
The third activities C and the fourth D are carried out by one group
Fifth activity E is carried out by two groups, the first from the beginning of the road and the second from its end, on the condition that the work ends on the same day
Activity F is executed from one working group for Activities C, D, E, and F Use the relationships SS = 2days or FF = 2days
Tests:
The second activity B requires a five-day check-up and is conducted twice (every half of the day)
The road alone.
Fourth activity D requires a six-day check-up and is conducted in two times (each half of the road alone.
Required :