Question: The ABCCo. factory has been having a maintenance problem with the control panel for one of its production processes. This control panel contains four identical

The ABCCo. factory has been having a maintenance problem with the control panel
for one of its production processes. This control panel contains four identical
electromechanical relays that have been the cause of the trouble. The problem is
that the relays fail fairly frequently, thereby forcing the control panel (and the
production process it controls) to be shut down while a replacement is made. The
current practice is to replace the relays only when they fail. The average total cost of
doing this has been Rs.320 per hour.
To attempt to reduce this cost, a proposal has been made to replace all four relays
whenever any one of them fails to reduce the frequency with which the control panel
must be shut down. Would this actually reduce the cost?
The pertinent data are the following. For each relay, the operating time until failure
has approximately a uniform distribution from 1,000 to 2,000 hours. The control panel
must be shut down for one hour to replace one relay or for two hours to replace all
four relays.
The total cost associated with shutting down the control panel and replacing relays
is Rs.1,00,000 per hour plus Rs.20,000 for each new relay. Develop a simulation
model to evaluate the cost of the proposal and compare it to the current practice.
Perform 10 trials (where the end of each trial coincides with the end of a shutdown
of the control panel) and determine the average cost per hour.
)
 The ABCCo. factory has been having a maintenance problem with the

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!