Question: The above network diagram has five paths. The paths and their durations are as follows: 1. Start >A>B>C> End {duration: days. } 2. Start D>E>F>

The above network diagram has five paths. The paths and their durations are as follows: 1. Start >A>B>C> End \{duration: days. \} 2. Start D>E>F> End \{duration: days.\} 3. Start D>B>C> End \{duration: days.\} 4. Start >G>H>> End \{duration: days.\} 5. Start > G -> E ->F -> End \{duration: days.\} The first path is the longest, it is the . The float on th The above network diagram has five paths. The paths and their durations are as follows: 1. Start >A>B>C> End \{duration: days. \} 2. Start D>E>F> End \{duration: days.\} 3. Start D>B>C> End \{duration: days.\} 4. Start >G>H>> End \{duration: days.\} 5. Start > G -> E ->F -> End \{duration: days.\} The first path is the longest, it is the . The float on th