Question: The above table is a project WBS with cost apportioned by percentages. The total project cost is estimated to be $600,000. What would be the

The above table is a project WBS with cost apportioned by percentages. The total project cost is estimated to be $600,000. What would be the the estimated costs for: 1) Design, 2) Programming, 3) In-house testing, 4) Inputs and Outputs, and 5) Interfaces and Files?
Also, what weaknesses are inherent in the estimating approach for the above figure?