Question: The activities described by the following table are given for the Howard Corporation in Kansas: Time Immediate Time Immediate Time Immediate Activity (in weeks) Predecessor(s)
The activities described by the following table are given for the Howard Corporation in Kansas: Time Immediate Time Immediate Time Immediate Activity (in weeks) Predecessor(s) Activity (in weeks) Predecessor(s) Activity (in weeks) Predecessor(s) A 10 B 6 C 3 A A This exercise contains only parts b and c. b) The activities on the critical path are B G H DEE 8 E 10 F 5 C BC 7 53 E, F D G, H c) The total project completion time for Howard Corporation is 32 weeks. (Enter your response as a whole number.)