Question: The activities described by the following table are given for the Howard Corporation in Kansas: Time Immediate Time Immediate Time Immediate Activity (in weeks) Predecessor(s)

The activities described by the following table are given for the Howard Corporation in Kansas: Time Immediate Time Immediate Time Immediate Activity (in weeks) Predecessor(s) Activity (in weeks) Predecessor(s) Activity (in weeks) Predecessor(s) A 10 6 B G 5 EF B 8 E 8 B H 6 D 6 F 5 3 G H This exercise contains only parts b and c. b) The activities on the critical path are c) The total project completion time for Howard Corporation is weeks. (Enter your response as a whole number) Enter your answer in the answer box