Question: The activities described by the following table are given for the Duplaga Corporation: Draw the network diagram and find the critical path. What is the
- The activities described by the following table are given for the Duplaga Corporation: Draw the network diagram and find the critical path. What is the expected completion time? (15 points)
|
Activity | Immediate Predecessor |
Time (days) |
| A | -- | 9 |
| B | A | 7 |
| C | A | 3 |
| D | B | 6 |
| E | B | 9 |
| F | C | 4 |
| G | E,F | 6 |
| H | D | 5 |
| I | G,H | 3 |