Question: The Activities needed to develop a new software application are listed in the following table with the activity times and their order in which the
The Activities needed to develop a new software application are listed in the following table with the activity times and their order in which the activities need to be performed.
Activity Duration. Immediate Predecessors
A. 1. -
B. 6. A
C. 5. A
D 10. A
E. 4. A
F. 11. B,C
G. 11. D,E
H. 5. F,G
Part 1. What is the earliest week you could finish activity F?
Part 2. What is the latest week you could start activity A?
Part 3. What is the latest week you could finish activity C?