Question: The activity details and their predecessors are given below along with their activity times. Construct the network diagram (1 Mark). Find out the critical path
The activity details and their predecessors are given below along with their activity times. Construct the network diagram (1 Mark). Find out the critical path ( 0.5Mark and project duration (0.5 Mark