Question: The Activity - On - Node network relationships and direct cost information of a small project are given on the next page. The indirect cost
The Activity
On
Node network relationships and direct cost information of a small project are given on the next page. The indirect cost for this project is $
day
The contract requires that the project be completed within
working days. A penalty of $
day will be imposed for each day of overrun.
You, the project manager, are responsible to make adjustments to the schedule in order to meet the requirement at a minimum cost.
Using time
cost adjustment,