Question: The Activity - On - Node network relationships and direct cost information of a small project are given on the next page. The indirect cost
The ActivityOnNode network relationships and direct cost information of a small project are given on the next page. The indirect cost for this project is $day The contract requires that the project be completed within working days. A penalty of $day will be imposed for each day of overrun.
You, the project manager, are responsible to make adjustments to the schedule in order to meet the requirement at a minimum cost.
Using time cost adjustment,
Plot a minimum direct cost curve, indirect cost, and total cost curve for the project, and identify normal, crash, and all crash points on the curves.
When and at what cost will this project be completed after your adjustments? State the reasons to support your decision.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock