Question: The answer is not 3. The formula that should be used is minimhm number of workstations= sum of the Task Times /Cycle Time The excessive




This exercise only contains parts b,c,d, e, and f. b) Given the demand, the cycle time for the production of the new train set = 32 seconds (round your tesponse to ane decima/ place). c) The theoretical minimum number of workstations = (round your response up to the next whole number). umber of n Please copy and paste data from text area halow re a new train set, the production of which is broken into six steps. The demand for the train is 4,500 units per 40 -hour work in of the new train set = seconds (round your response to one decimal place). (round your response up to the next whale number). This exercise only contains parts b,c,d;e, and f. b) Given the demand, the cycle time for the production of the new train set = seconds (round your response fo ane decimal place). c) The theoretical minimum number of workstations = (round your response up to the next whole number)
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts