Question: The answer is not B, please help Use the following partially completed MRP record to answer the question. ITEM: XYZ Description: Lot Size P =

The answer is not B, please helpThe answer is not B, please help Use the

Use the following partially completed MRP record to answer the question. ITEM: XYZ Description: Lot Size P = 2 Lead Time: 1 week 2 7 1 100 3 50 4 70 5 40 6 90 8 50 100 Date Gross requirements Scheduled receipts Projected on Hand 0 Planned receipts Planned order releases What is the planned order release quantity in week 4? A. Greater than 50 units but fewer than or equal to 100 units B. Greater than 0 units but fewer than or equal to 50 units C. Greater than 100 units D. O units