Question: The AOA network for a certain project is given in the graph below with the task durations (in days) in the table beneath it. The
The AOA network for a certain project is given in the graph below with the task durations (in days) in the table beneath it. The activities d1 and d2 are dummy activities.
What is the slack for activity g?
| Activity | a | b | c | d | e | f | g | h |
| Duration | 6 | 15 | 10 | 5 | 3 | 1 | 9 | 8 |
| 7 days | ||
| None of the other options are correct | ||
| 12 days | ||
| -15 days | ||
| 0 days |
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
