Question: The AOA network for a certain project is given in the graph below with the task durations (in days) in the table beneath it. The

The AOA network for a certain project is given in the graph below with the task durations (in days) in the table beneath it. The activities d1 and d2 are dummy activities.

The predecessors for activity e are:

Activity

a

b

c

d

e

f

g

h

Duration

8

12

8

5

5

10

7

0

The AOA network for a certain project is given in

How many paths are there from start to finish?

What activities are on the critical path?

What is the duration of this project?

What is the slack for activity g?