Question: The AON Network is associated with teh activities (A through H) for the Carl Betterton's construction project. The AON network shows a sequence of activites
The AON Network is associated with teh activities (A through H) for the Carl Betterton's construction project. The AON network shows a sequence of activites and a task time (days) for each activity.

I have completed the immediate predecessor section as well as the time section in the above table. I have also run this in LibreProject and I found a project length of 23 days. I have found a critical path of A,C,F,H but I am having issues with completing the EF and LF.
Can you guide me in the right direction?
Problem solving: The AON network is associated with the activities (A through H) for the Carl Betterton's construction project. The AON network shows a sequence of activities and a task time (days) for each activity. 6 6 D G B 9 End E H Start A 4 F 1) (45 pts). Complete the following table: Activity Time EF LF Slack Critical? Immediate predecessor(s) A N/A 4 B A 4 A 6 D B 6 E B 4 F 4 G D 6 H E.F 9 2) (15 pts). Critical path: 3) (5 pts). Project lengthStep by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts