Question: The approved project baseline schedule should be changed when? Project spent more than planned on several activities An activity on the critical path has taken

The approved project baseline schedule should be changed when?
Project spent more than planned on several activities
An activity on the critical path has taken longer than scheduled
Some changes to the project scope, cost, or schedule have been approved
Project is running ahead of schedule