Question: The average hourly labor cost for a construction masonry crew consisting of one foreman, six masons, and nine helpers is $18/workhour, and the net productivity

The average hourly labor cost for a construction
The average hourly labor cost for a construction masonry crew consisting of one foreman, six masons, and nine helpers is $18/workhour, and the net productivity is 0.018 workhours per brick. Brick dimensions are 2-5/8" X 8" X 3-1/2". This crew is building a masonry wall whose net area is 18,018 square feet. This crew works 7 hours per day. 1. What is the labor cost for this wall? 2. What is the daily consumption of bricks? (assume no waste)