Question: The average wait time before starting an order at the machining workcell is 2 hours. It then takes an average of 25 minutes to set

The average wait time before starting an order at
The average wait time before starting an order at the machining workcell is 2 hours. It then takes an average of 25 minutes to set up the cell for the order. The machine cycle time on each part is 120 seconds. If a container holds 20 parts, management allows a 20% safety margin, and 8 containers have been allocated for the part, how much average daily demand can the machining cell handle? Use the unite (Units/day). Note the day = 8 hours. =