Question: The backward pass in project network calculations determines the: a . Latest times that activities can begin. b . Earliest times that activities can be

The backward pass in project network calculations determines the:
a.
Latest times that activities can begin.
b.
Earliest times that activities can be finished.
c.
Critical path
d.
Both a and c are correct