Question: The backward pass in project network calculations determines the A . Latest time's activities can begin B . Earliest time's activities can be finished C

The backward pass in project network calculations determines the
A. Latest time's activities can begin
B.Earliest time's activities can be finished
C.Critical path
D. Both A and C are correct
E.A, B, and C are all correct