The Batre Bicycle Company makes everyday bicycles from recycled materials. The following data is available for July
Fantastic news! We've Found the answer you've been seeking!
Question:
The Batre Bicycle Company makes everyday bicycles from recycled materials. The following data is available for July of the current year: Amount of direct labor used 460 hrs. Actual direct labor rate $12.2 per hour. Bicycles finished in April 220 bicycles Standard direct labor per bicycle 2 hrs. Standard rate for direct labor $12.4 per hour.
Required
a. Determine the direct labor rate variance, the direct labor time variance, and the direct labor total cost variance.
Rate variance $ Time variance $ Total direct labor cost variance $
b. How much direct labor should be charged to Work in Process?