The below project is at the end of its eleventh week. Find CV, SV, SPI, CPI, ETC
Fantastic news! We've Found the answer you've been seeking!
Question:
The below project is at the end of its eleventh week. Find CV, SV, SPI, CPI, ETC and EAC for the project. Discuss the results.
Activity | before | Duration- (WEEK) | Budget ($) | Actual Cost ($) | % complete |
A | - | 4 | 250 | 350 | 100 |
B | - | 3 | 180 | 190 | 100 |
C | A | 5 | 320 | 290 | 100 |
D | B | 4 | 560 | 620 | 100 |
E | C | 4 | 450 | 230 | 20 |
F | D | 5 | 200 | 50 | 20 |
G | E,F | 7 | 275 | - | 0 |
Related Book For
Project Management in Practice
ISBN: 978-0470533017
4th edition
Authors: Samuel J. Mantel Jr., Jack R. Meredith, Sco
Posted Date: