Question: The below table gives the processing times ( in hours ) of seven jobs to be processed on four machines M 1 , M 2

The below table gives the processing times (in hours) of seven jobs to be processed on four machines M1, M2, M3 and M4 in the order M1,M2,M3,M4. Sequence the given jobs using Johnson's method and find the overall processing time.
\table[[,M1,M2,M3,M4],[A,3,1,4,12],[B,8,0,5,15],[C,11,3,8,10],[D,4,7,3,8],[E,5,5,1,10],[F,10,2,0,13],[G,2,5,6,9]]