Question: The Beta distribution is used to calculate a. expected activity times b. the probability that a project will be completed within its budget c. slack
The Beta distribution is used to calculate
a. expected activity times
b. the probability that a project will be completed within its budget
c. slack on activities
d. pessimistic and optimistic activity times
e. which activity should be crashed
The beta distribution is used by
a. Project Analysis
b. AON method
c. Locational break even analysis
d. CPM analysis
e. PERT analysis