Question: The Bloomington Bike Company produces two models: the Basic (B) and the Supra (S). Herb Hoosier, the owner, plans to assemble 20 Basics (B) and

The Bloomington Bike Company produces two models: the Basic (B) and the Supra (S). Herb Hoosier, the owner, plans to assemble 20 Basics (B) and 15 Supras (S) in each week during periods 6 to 8. Bill of materials (BOM) for each bike and data on all lead times, current inventory and ordering rules are given below. Suppose there are no schedule receipts. Develop a materials requirement plan for these components over the next 8 weeks.
BOM.jpg
| ITEM | LEADTIME (WKS) | ON HAND | LOT-SIZING RULE |
| B | 2 | 5 | Lot-for-lot |
| S | 2 | 2 | Multiples of 20 |
| X | 1 | 5 | Multiples of 25 |
| W | 1 | 0 | Multiples of 12 |
| F | 1 | 0 | Lot-for-lot |
| K | 1 | 3 | Multiples of 20 |
| Q | 1 | 15 | Multiples of 30 |
What is the Planned order release for item X in week 4?
0
15
25
50
What is the gross requirments for item F in week 5?
75
95
165
185
B S W F X(2) Q | F(3) K(2) 1 W(3)Step by Step Solution