Question: The Bloomington Bike Company produces two models: the Basic (B) and the Supra (S). Herb Hoosier, the owner, plans to assemble 20 Basics (B) and
The Bloomington Bike Company produces two models: the Basic (B) and the Supra (S). Herb Hoosier, the owner, plans to assemble 20 Basics (B) and 15 Supras (S) in each week during periods 6 to 8. Bill of materials (BOM) for each bike and data on all lead times, current inventory and ordering rules are given below. Suppose there are no schedule receipts. Develop a materials requirement plan for these components over the next 8 weeks.
| ITEM | LEADTIME (WKS) | ON HAND | LOT-SIZING RULE |
| B | 2 | 5 | Lot-for-lot |
| S | 2 | 2 | Multiples of 15 |
| X | 1 | 5 | Multiples of 25 |
| W | 1 | 0 | Multiples of 12 |
| F | 1 | 0 | Lot-for-lot |
| K | 1 | 3 | Multiples of 20 |
| Q | 1 | 15 | Multiples of 30 |
What is the Gross requirements for item F in week 4?
| 50 | ||
| 150 | ||
| 165 | ||
| 185 |