Question: The BOM for item A is given below. Complete the MRP records for all of the components. The planning factor information for each component is
The BOM for item A is given below. Complete the MRP records for all of the components. The planning factor information for each component is given in a table below.
The Master Production Schedule for A indicates the following start times and quantities:
100 week 2
150 week 3
250 week 7
Inventory Record information
|
| Item B | Item C | Item E |
| Lot-sizing rule | FOQ = 300 units | POQ = 2 weeks | LFL |
| Scheduled Receipts | None | None | 300 (week 1) |
| Beginning Inventory | 250 | 450 | 100 |
| Safety Stock | 0 | 0 | 40 |
| Lead time | 1 week | 1 week | 1 week |
You can use the following table template to develop MRP tables for Item B, Item C, and Item E on the paper. After you finish the MRP tables, upload the file here.
| Lot Size: Item: Lead Time: Description: Safety Stock: | ||||||||
| Date | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 |
| Gross requirements |
|
|
|
|
|
|
|
|
| Scheduled receipts |
|
|
|
|
|
|
|
|
| Projected on hand |
|
|
|
|
|
|
|
|
| Planned receipts |
|
|
|
|
|
|
|
|
| Planned order releases |
|
|
|
|
|
|
|
|
-