Question: The BOM for product A, and data from the inventory records, are shown below. In the master production schedule for product A, the MPS quantity

The BOM for product A, and data from the inventory records, are shown below. In the master production schedule for product A, the MPS quantity row (showing completion dates) calls for 300 units in week 8. The lead time for production of A is two weeks.

Data Category B C D
Lot sizing rule P = 2 FOQ = 1,200 LFL
Lead time 3 weeks 3 weeks 1 week
Scheduled receipts 60 (week 2) 0 0
Beginning (on-hand) inventory 0 110 0

Develop the materials requirements plan for the next eight weeks for Items B, C, and D. Round your answers to the nearest whole number. Do not leave fields blank, enter zero if applicable.

MPS Lead time = 2 weeks for assembly
Week 1 2 3 4 5 6 7 8
Product Aend item
Planned order releases

Item C (two units of C are needed for one unit of A) Lot size: 1,200 units
Description Lead time: 3 weeks
Week 1 2 3 4 5 6 7 8
Gross requirements
Scheduled receipts
Projected OH inventory 110
Planned order receipts
Planned order releases

Item D Lot size: LFL
Description Lead time: 1 week
Week 1 2 3 4 5 6 7 8
Gross requirements
Scheduled receipts
Projected OH inventory 0
Planned order receipts
Planned order releases

Item B Lot size: POQ = 2 weeks
Description Lead time: 3 weeks
Week 1 2 3 4 5 6 7 8
Gross requirements
Scheduled receipts
Projected OH inventory 0
Planned order receipts
Planned order releases

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!