Question: The Budget at Completion ( BAC ) for a project is $ 6 0 , 0 0 0 and the Actual Costs ( AC )

The Budget at Completion (BAC) for a project is $60,000 and the Actual Costs (AC) to date are $15,000 with Earned Value (EV) of $12,000. At this stage, the project management team did a manual bottom-up summation of costs and forecast an Estimate to Complete (ETC) of $47,000. What is the Estimate at Completion (EAC) for the project?
Correct Answer
a)
$62,000
b)
$66,000
Incorrect Response
c)
$75,000
d)
$64,000

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!