Question: The Budget at Completion ( BAC ) for a project is $ 6 0 , 0 0 0 and the Actual Costs ( AC )
The Budget at Completion BAC for a project is $ and the Actual Costs AC to date are $ with Earned Value EV of $ At this stage, the project management team did a manual bottomup summation of costs and forecast an Estimate to Complete ETC of $ What is the Estimate at Completion EAC for the project?