Question: The charter for a new project includes the approved project approach (hybrid), the expected net benefit (US $40,000/year), and the names of the sponsor, part
The charter for a new project includes the approved project approach (hybrid), the expected net benefit (US $40,000/year), and the names of the sponsor, part time product owner, and project manager. How will the product value be communicated to the team? A. . C. From the product owner using a backlog list. From the project manager using the WBS. From the stakeholders who attend iteration review meetings. From the sponsor through the charter