Question: The client has expressed concern about excessive risks in some project deliverables. When budgeting projects using Agile methods, which term BEST describes the short, time

The client has expressed concern about excessive risks in some project deliverables. When budgeting projects using Agile methods, which term BEST describes the short, time-boxed effort to test the concept to reduce risk?
a. Spike
b. Shift left
c. Analogous estimating
d. Parametric estimating