Question: The client has expressed concern about excessive risks in some project deliverables. When budgeting projects using Agile methods, which term BEST describes the short, time-boxed
The client has expressed concern about excessive risks in some project deliverables. When budgeting projects using Agile methods, which term BEST describes the short, time-boxed effort to test the concept to reduce risk? a. Spike b. Shift left c. Analogous estimating d. Parametric estimating