Question: The client is seeking information about the risk management processes employed by the team. When determining project progress and results using Agile methods, how is
The client is seeking information about the risk management processes employed by the team. When determining project progress and results using Agile methods, how is risk managed? a. The change control board chairperson prioritized the work. b. PM and team track and identify risks and implement resolution strategies. c. PM and team track and identify risks and implement resolution strategies, plus team manages workflow. d. The change control board chairperson prioritized the work then the PM and team track and identify risks and implement resolution strategies, plus team manages workflow