Question: the completion time of a project es expected to be 44 weeks, with a standard diviation of 2.67 weeks. what is the probability the project

the completion time of a project es expected to be 44 weeks, with a standard diviation of 2.67 weeks. what is the probability the project will not be completed in 52 weeks or less?99.865.5none