Question: The completion times for the activities are given below: Activity Time (Weeks) A 6 B 3 C 6 D 15 E 12 The latest finish

The completion times for the activities are given below: Activity Time (Weeks) A 6 B 3 C 6 D 15 E 12 The latest finish time for A will be: a. 6 b. 9 c. 12 d. 24 Earliest