Question: A certain project has the following precedence relationships. Activity Immediate Predecessor(s) A - B - C A D C E A, B F D G

A certain project has the following precedence relationships.

Activity Immediate Predecessor(s)
A -
B -
C A
D C
E A, B
F D
G D, E
H F, G

The activity times are as follows:

Activity Activity Time (weeks)
A 6
B 9
C 6
D 12
E 11
F 4
G 4
H 8
How long is this project expected to last?
Calculate the earliest start/earliest finish, latest start/latest finish, and slack for each activity. Indicate them in a form of a network diagram