Question: A certain project has the following precedence relationships. Activity Immediate Predecessor(s) A - B - C A D C E A, B F D G
A certain project has the following precedence relationships.
| Activity | Immediate Predecessor(s) |
|---|---|
| A | - |
| B | - |
| C | A |
| D | C |
| E | A, B |
| F | D |
| G | D, E |
| H | F, G |
The activity times are as follows:
| Activity | Activity Time (weeks) |
|---|---|
| A | 6 |
| B | 9 |
| C | 6 |
| D | 12 |
| E | 11 |
| F | 4 |
| G | 4 |
| H | 8 |
Calculate the earliest start/earliest finish, latest start/latest finish, and slack for each activity. Indicate them in a form of a network diagram