Question: The Consider the following single machine-scheduling problem. The minimum mean flow time of this problem is Job (1) 1 Processing time (t) in 15 5


The Consider the following single machine-scheduling problem. The minimum mean flow time of this problem is Job (1) 1 Processing time (t) in 15 5 12 hours 2 3 4 5 6 7 16 11 9 10 The minimum mean flow time of this problem is Select one: The minimum mean flow time of this problem is O Select one: a. 35.5 hours b. 40.50 hours c. 30.85 hours d. 37.85 hours