Question: the constraints? a . Possible Solution b . Feasibie region c . Objective Function d . Cost minimization region Which of the Following is the
the constraints?
a Possible Solution
b Feasibie region
c Objective Function
d Cost minimization region
Which of the Following is the term used for the tquation that mint se aptumised wid a governed by constraints?
a Bounded Region
b Objective Function
c Center point
d Linear Programming
You are an experienced project manager All of the following terms descrbe whomens: time included in the schedule to account for uncertainty except for which one?
a Contingency
b Feasble Time
c Reserve
d Buffer
is a network diagramming technique used to predict total project duration.
a PERT
b A Gantt Chart
c Critical Path Method
d Crashing
You are working on your network diagram. Activity is a predecessor to Activity B Activity B cannot begin until Activity A is completed. What is this telling you?
a There is a finishtostart dependency relationship between Activity A and Activity
c Activity A and Activity are both on the critical path.
d Activity B is a successor to multiple tasks.
Extra Credit: In developing the schedule management plan which of the following too will the project manager use?
a Data Representation
b Data Analysis
c Decision Making
d Project Management Information System
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock