Question: the constraints? a . Possible Solution b . Feasibie region c . Objective Function d . Cost minimization region Which of the Following is the

the constraints?
a. Possible Solution
b. Feasibie region
c. Objective Function
d. Cost minimization region
Which of the Following is the term used for the tquation that mint se aptumised wid a governed by constraints?
a. Bounded Region
b. Objective Function
c. Center point
d. Linear Programming
You are an experienced project manager All of the following terms descrbe whomens: time included in the schedule to account for uncertainty except for which one?
a. Contingency
b. Feasble Time
c. Reserve
d. Buffer
12)q, is a network diagramming technique used to predict total project duration.
a. PERT
b. A Gantt Chart
c. Critical Path Method
d. Crashing
You are working on your network diagram. Activity A is a predecessor to Activity B. Activity B cannot begin until Activity A is completed. What is this telling you?
a. There is a finish-to-start dependency relationship between Activity A and Activity B.
c. Activity A and Activity B are both on the critical path.
d. Activity B is a successor to multiple tasks.
Extra Credit: In developing the schedule management plan which of the following too will the project manager use?
a. Data Representation
b. Data Analysis
c. Decision Making
d. Project Management Information System
 the constraints? a. Possible Solution b. Feasibie region c. Objective Function

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!