Question: The controller for Wolfe Machining has established the following overhead cost pools and cost drivers : Overhead cost Pool Budgeted overhead cost cost driver Machine
The controller for Wolfe Machining has established the following overhead cost pools and cost drivers:
| Overhead cost Pool | Budgeted overhead cost | cost driver |
| Machine setups | $240,000 | number of setups |
| Material Handling | 90,000 | Units of raw material |
| Quality control inspection | 48,000 | Number of inspection |
| Other overhead costs | 160,000 | machine hours |
| total | $538,000 |
| Over Head cost pool | Budgeted Level for Cost driver | Pool Rate |
| Machine setups | 200 setups | $1,200 per setup |
| Material Handling | 60,000 units | $1.50 per unit |
| Quality Control | 1,200 inspections | $40 per inspection |
| Other overhead | 20,000 machine hours | $ 8 per machine hour |
Order no. 715 has the following production requirements: Machine setups: 5 Raw material: 10,700 units Inspections: 19 Machine hours: 790 a.[10 points] Compute the total overhead that should be assigned to order no. 715 by using activity-based costing.
b. [10 points] Suppose that Wolfe were to use a single, predetermined overhead rate based on machine hours. Compute the rate per hour and the total overhead assigned to order no. 715. .