Question: the correct answer for the question I gave you for: A production line is to be designed for a job with three tasks. The task
the correct answer for the question I gave you for: A production line is to be designed for a job with three tasks. The task times are .4 minutes, 1.2 minutes, and .5 minutes. The maximum cycle time in minutes is: 0.4 0.5 1.2 2.1 3 the correct answer is 2.1