Question: The _ _ _ _ _ _ cost and duration estimation technique starts at the lowest level of detail in the WBS . For each

The ______ cost and duration estimation technique starts at the lowest level of detail in the WBS. For each low-level task, a work content estimate is prepared based on the nature of the individual task. These individual task estimates are aggregated into the overall project estimate.
A. top-down
B. bottom-up
C. parametric
D. template