Question: The cost data for project X is given below: Year O (Now): $100,000 Yearl: 10,000$ Year 2:12,000$ and Year 3:14,000$ The benefits are quantified as:
The cost data for project X is given below: Year O (Now): $100,000 Yearl: 10,000$ Year 2:12,000\$ and Year 3:14,000$ The benefits are quantified as: Year 0 (Now): $0 Year 1:\$50,000 Year2: $60,000 and Year 3:70,000$ The discount rate is 5%. Compute the NPV for this project \begin{tabular}{|c|} \hline$30007.6 \\ \hline$27000 \\ \hline$51000.8 \\ \hline$62008.2 \end{tabular}