Question: The cost data for project X is given below: Year 0 (Now): $100,000 Year1: 10,000$ Year 2: 12,000$ and Year 3: 14,000$ The benefits are

The cost data for project X is given below: Year 0 (Now): $100,000 Year1: 10,000$ Year 2: 12,000$ and Year 3: 14,000$ The benefits are quantified as: Year 0 (Now): $0 Year 1:$50,000 Year2: $60,000 and Year 3: 70,000$ The discount rate is 4%. The ROI for this project is: 0 24.5% 0 28.5% 0 31.5% o 22.5%