Question: The critical chain is: a . The longest duration path through the project b . The most resource - constrained path through the project c
The critical chain is:
a The longest duration path through the project
b The most resourceconstrained path through the project
c The path through the project that is the most taskdependent and resource constrained
d The path through the project that is the most resource constrained and has the longest duration