Question: The critical path for the network activities shown below is -- with completion time of weeks. Activity Preceding Time A -- 10 B -- 8

The critical path for the network activities shown below is -- with completion time of weeks.

Activity

Preceding

Time

A

--

10

B

--

8

C

A

2

D

A

4

E

B, C, D