Question: asap The critical path for the network activities shown below is with duration A-B-D; 10 weeks A-D-E; 13 weeks C-E; 12 weeks A-B-C-D-E;22 weeks A-B-E;

asap
asap The critical path for the network activities
The critical path for the network activities shown below is with duration A-B-D; 10 weeks A-D-E; 13 weeks C-E; 12 weeks A-B-C-D-E;22 weeks A-B-E; 11 weeks