Question: The critical path for the project in Table 1 below is A-D-F-G-H and the duration for this project is 24 months. Using the information provided

The critical path for the project in Table 1 below is A-D-F-G-H and the duration for this project is 24 months. Using the information provided and the Standard Normal Distribution Table in the appendix, calculate the probability of this project being completed in 21 months. (Give your answers to 2 decimal places and show all workings) (10 marks) CLO 3 Hint: Calculate the estimated duration of the activities using the beta distribution, Calculate the standard deviation for the project, Calculate the projects Z value, and identify that value on the Standard Normal Distribution