Question: The critical path in a PERT chart represents: Multiple Choice the tasks that must be completed without errors. the most important tasks of the whole

The critical path in a PERT chart represents:
Multiple Choice
the tasks that must be completed without errors.
the most important tasks of the whole project.
the sequencing of tasks.
the longest path of tasks needed for project completion.