Question: The critical path in a PERT chart represents: a. the sequencing of tasks. b. the most important tasks of the whole project. c. the longest

 The critical path in a PERT chart represents:

a. the sequencing of tasks.

b. the most important tasks of the whole project.

c. the longest path of tasks needed for project completion.

d. the tasks that must be completed without errors.

Step by Step Solution

3.47 Rating (160 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

c the longest path of tasks needed for project completion In a PERT Program Evaluation and Rev... View full answer